Which command should you use?

You use bottom-up scheduling. You need to group four consecutive tasks in a major phase.
You highlight the four tasks. Which command should you use?

You use bottom-up scheduling. You need to group four consecutive tasks in a major phase.
You highlight the four tasks. Which command should you use?

A.
Outdent

B.
Fill Down

C.
Insert Summary

D.
Move Task

Explanation: