Which two actions should you perform?

You use Project Professional 2010 to manage a software development project as shown in
the exhibit. (Click the Exhibit button.)

You need to cancel the Develop prototype based on functional specifications task. You also
need to retain all the information from the task. Which two actions should you perform?
(Each correct answer presents part of the solution. Choose two.)

You use Project Professional 2010 to manage a software development project as shown in
the exhibit. (Click the Exhibit button.)

You need to cancel the Develop prototype based on functional specifications task. You also
need to retain all the information from the task. Which two actions should you perform?
(Each correct answer presents part of the solution. Choose two.)

A.
Delete the task.

B.
Set the tasks remaining work to 0 hours.

C.
Inactivate the task.

D.
Make the task 100 percent complete.

E.
Create a link from the Develop functional specifications task to the Review functional
specifications task.