You need to identify the problem

You enter the finish date for a task, and then assign a resource. You discover that the task is
automatically scheduled for two weeks past the finish date you have entered. You need to
identify the problem. What should you do?

You enter the finish date for a task, and then assign a resource. You discover that the task is
automatically scheduled for two weeks past the finish date you have entered. You need to
identify the problem. What should you do?

A.
Click Calculate project

B.
Use the Task Inspector tool and view the start and finish dates

C.
Use the Task Inspector tool and view the resource calendar

D.
View the deadline date for the task

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *