Your project contains many tasks that have dependencies and result in independent
networks of tasks. You need to ensure that you can view critical tasks on all independent
networks of tasks within the project. What should you do?
A.
View the project’s Gantt chart and apply the Critical filter.
B.
On the Advanced tab of the Microsoft Project 2010 options, select the Calculate multiple
critical paths check box.
C.
View the project’s Gantt chart and apply the Critical group.
D.
On the Advanced tab of the Microsoft Project 2010 options, modify the Tasks are critical if
slack is less than or equal to option.