You need to ensure that when you add new tasks, the project schedule doesn’t set a start date and end date

You need to ensure that when you add new tasks, the project schedule doesn’t set a start
date and end date. What should you do?

You need to ensure that when you add new tasks, the project schedule doesn’t set a start
date and end date. What should you do?

A.
Select Task from the main ribbon menu. Highlight the task that you want to change and
select Manually Schedule.

B.
On the Schedule tab of the Project options, change the New tasks created option to
Manually Scheduled.

C.
On the Advanced tab of the Project options, clear the Automatically add new resources
and tasks check box.

D.
On the Display tab of the Project options, clear the Edits to start and finish dates check
box.

E.
Click New Tasks and change the option to Auto Scheduled.

Explanation: