Your project has a part-time resource who works 4 hours a day from Monday through
Thursday. You need to ensure that your project plan accommodates the part-time resource.
What should you do?
A.
Update the base project calendar.
B.
Change the working time for the resource.
C.
Change the maximum units for the resource.
D.
Assign the resource only to tasks that are scheduled on the working days.