You need to incorporate the task outline into your project plan

You receive a Microsoft Outlook e-mail message that contains the following task outline:
• Establish corporate internal communications process.
• Find out the regional and country divisions’ communications process.
• Plan communication methods, logistics, and timings.
• Establish regional and country communications to sales, marketing, and
management.
• Find out the internal systems that must respond to the campaign.
• Create communications plan.
• Identify internal training requirements.
• Develop internal training.

• Organization of internal communications and training completion.
You need to incorporate the task outline into your project plan. What should you do?

You receive a Microsoft Outlook e-mail message that contains the following task outline:
• Establish corporate internal communications process.
• Find out the regional and country divisions’ communications process.
• Plan communication methods, logistics, and timings.
• Establish regional and country communications to sales, marketing, and
management.
• Find out the internal systems that must respond to the campaign.
• Create communications plan.
• Identify internal training requirements.
• Develop internal training.

• Organization of internal communications and training completion.
You need to incorporate the task outline into your project plan. What should you do?

A.
Use the Bulk Import tool from the Project 2010 Solution Starters toolkit.

B.
Copy and paste the task outline into the Task Sheet view of Project 2010.

C.
Use the Task Inspector feature from Outlook.

D.
Use the Import Outlook Tasks option.