You create several new tasks by using the Manually Scheduled Task option. You need to
automatically calculate the start and finish dates for linked manually scheduled tasks. You
need to achieve this goal while retaining manually scheduled tasks within the project. What
should you do?
A.
Modify the values of Scheduled Start and Scheduled Finish.
B.
Highlight the Project Summary task and use the Calculate Project feature.
C.
Insert the task Constraint Type column and change the values for each task to the
appropriate values. Then, recalculate the project.
D.
Use the Respect Links feature.