You need to update the project schedule to reflect the change

John, a team member, will be absent from the team. A new team member, Mary, will take
over Johns remaining work. You need to update the project schedule to reflect the change.
You also need to retain John’s actual work. What should you do?

John, a team member, will be absent from the team. A new team member, Mary, will take
over Johns remaining work. You need to update the project schedule to reflect the change.
You also need to retain John’s actual work. What should you do?

A.
In the Assign Resources dialog box, use the Replace feature.

B.
In the Resource Sheet view, delete John and add Mary.

C.
In the Multiple Task Information dialog box, change the resource assignment from John to
Mary.

D.
In the Resource Usage view, rename John to Mary.



Leave a Reply 0

Your email address will not be published. Required fields are marked *