Standard working hours are eight hours a day from Monday through Friday. You create a
task of fixed units and set the duration to 2 days. You assign the task to John at 100 percent.
John wants to work only 50 percent on the task. You change John’s assignment units to 50
percent for the task. Which set of values describes the specified task?
A.
Duration shows 2 days; Work shows 0 hours
B.
Duration shows 4 days; Work shows 16 hours
C.
Duration shows 4 days; Work shows 8 hours
D.
Duration shows 2 days; Work shows 8 hours
E.
Duration shows 2 days; Work shows 16 hours