You need to replace the resource assignment for an in-progress task

You need to replace the resource assignment for an in-progress task. You also need to
retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should
you do?

You need to replace the resource assignment for an in-progress task. You also need to
retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should
you do?

A.
Use the Resource Name column drop-down list.

B.
Use the Resource Pool feature.

C.
Use the Team Planner feature.

D.
Use the Level Selected feature.



Leave a Reply 0

Your email address will not be published. Required fields are marked *