You need to view the following information for your project:
• Current cost
• Baseline cost
• Actual cost
• Remaining cost
• Percentage of completion
Which component will display the information?
A.
The default Resource Sheet
B.
The default Task Sheet
C.
The Project Statistics window
D.
The default Cost Table