You need to link the project schedules at the task level

You manage several projects saved on a shared drive. You want to create a critical path
relationship between several schedules managed by other project managers. You need to
link the project schedules at the task level. You also need to ensure that each project
manager can continue to manage their own project. What should you do?

You manage several projects saved on a shared drive. You want to create a critical path
relationship between several schedules managed by other project managers. You need to
link the project schedules at the task level. You also need to ensure that each project
manager can continue to manage their own project. What should you do?

A.
• Open each individual project.
• Create date constraints for task deadlines.
• Save the project.

B.
• Open a blank project.
• Insert each project and select the Link to project option.
• Link tasks as needed.
• Save the subprojects.

C.
• Open a blank project.
• Copy and paste each project into the new file.
• Link tasks as needed.
• Save the project by using a new name.

D.
• Open a blank project.
• Insert each project and select the Link to project option.
• Save the blank project as a new named project.
• Discard the subprojects.

E.
• Open a blank project.
• Insert each project and clear the Link to project option.
• Save the blank project as a new named project.
• Discard the subprojects.

Explanation: