You receive approval for a project plan that is yet to start. You need to ensure that all project
tasks start no earlier than September 13, 2010. Which project level field should you set?
A.
Change the Status Date field to 9/13/2010.
B.
In the Current Date field, type 9/13/2010.
C.
In the Start Date field, type 9/13/2010.
D.
Change the calendar type in the Project Options dialog box.