You have a task named Tasks that has a duration of four days and a finish-to-finish
relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You
also need to retain the original duration and resource assignments. You select Tasks. What
should you do next?
A.
Remove the predecessor assignments.
B.
Click the Insert Milestone button.
C.
Select the Mark Task as Milestone check box.
D.
Change Work to zero hours.