You need to reschedule all the remaining work on the project

All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You
need to reschedule all the remaining work on the project. You also need to achieve this goal
without having rigid constraints set to your project’s tasks. What should you do?

All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You
need to reschedule all the remaining work on the project. You also need to achieve this goal
without having rigid constraints set to your project’s tasks. What should you do?

A.
Click Update Project.

B.
Click Calculate Project.

C.
Change the Status Date field.

D.
Click Move Project.



Leave a Reply 0

Your email address will not be published. Required fields are marked *