You need to view only the tasks that currently affect the overall completion date

You have a project schedule in progress. You need to view only the tasks that currently
affect the overall completion date. What should you do in the Gantt Chart view?

You have a project schedule in progress. You need to view only the tasks that currently
affect the overall completion date. What should you do in the Gantt Chart view?

A.
Apply the Priority group.

B.
Apply the Incomplete Tasks filter.

C.
Apply the Late Tasks filter.

D.
Apply the Critical Tasks filter.

E.
Apply the Status group.



Leave a Reply 0

Your email address will not be published. Required fields are marked *