You need to compare the total work of your project’s deliverables against the baseline work

You need to compare the total work of your project’s deliverables against the baseline work.
What should you do?

You need to compare the total work of your project’s deliverables against the baseline work.
What should you do?

A.
From the Gantt Chart view, change the table to display the Work table.

B.
Use the Task Usage view and the Task Form in the details pane.

C.
From the Task Sheet view, change the table to display the Summary table.

D.
Use the Tracking Gantt view and display the default Entry table.