Your network contains a System Center 2012 Virtual Machine Manager (VMM) infrastructure. The infrastructure
contains 50 Hyper-V hosts.
You plan to deploy Power Optimization for VMM.
You need to prepare the infrastructure for the planned deployment.
What should you do? (Each correct answer presents part of the solution. Choose two.)
A.
Install a Baseboard Management Controller (BMC) on each Hyper-V host.
B.
Enable Dynamic Optimization.
C.
Enable Hibernation.
D.
Enable Performance and Resource Optimization (PRO).
E.
Install a configuration provider on each Hyper-V host.
Explanation:
A: To use Power Optimization, the host computers must have a BMC that enables out-of- band management.
B: Power Optimization is an optional feature of Dynamic Optimization, and it is only availablewhen a host group
is configured to migrate virtual machines through Dynamic Optimization.
http://technet.microsoft.com/en-us/library/gg675109.aspx