An offsite information processing facility having electrical wiring, air conditioning and flooring, but no computer or communications equipment is a:

An offsite information processing facility having electrical wiring, air conditioning and flooring, but
no computer or communications equipment is a:

An offsite information processing facility having electrical wiring, air conditioning and flooring, but
no computer or communications equipment is a:

A.
cold site.

B.
warm site.

C.
dial-up site.

D.
duplicate processing facility.

Explanation:

A cold site is ready to receive equipment but does not offer any components at the site in advance
of the need.