Quiz 70-633

Quiz 70-633, TS: Microsoft Office Project Server 2007, Managing Projects

You need to link the tasks in such a way that Task B can start any time after Task A starts

Where can you view availability of resources while you assign them to the project plan?

you need to reschedule the task to take 5 days

What should you ask the administrator of Project Server to do?

you need to track the fixed payment costs as they are incurred and include these payments in the project costs

you need to display the cost-to-date for each resource on this project

you need to update your published project plan with this information

You need to ensure that holiday time for each enterprise resource is accounted for in the project plan

you need to track this risk for the new tasks

you need to update the task so that dependent tasks will be rescheduled