Quiz 74-343

Quiz 74-343, Managing Projects with Microsoft Project 2013

Which three actions should you perform in sequence?

Which three actions should you perform in sequence?

you need to resolve the over allocation for Resource1 for the month of November only

However, the sponsor now asks that the project be delayed to have a finish date of December 31.

What should you do?

You need to set each task duration as estimated, until the estimate is confirmed by the assigned resource

You need to ensure that the effort for each resource and task is set up properly in the calendar

What happens in the resource pool after you delete the project?

You need to create a task which leveling will not change

You need to monitor this phase closely to ensure that it does not overrun