Which one of the following components is likely to be updated in the risk register based on their analysis?

Your project team has completed the quantitative risk analysis for your project work. Based on
their findings, they need to update the risk register with several pieces of information. Which one
of the following components is likely to be updated in the risk register based on their analysis?

Your project team has completed the quantitative risk analysis for your project work. Based on
their findings, they need to update the risk register with several pieces of information. Which one
of the following components is likely to be updated in the risk register based on their analysis?

A.
Listing of risk responses

B.
Risk ranking matrix

C.
Listing of prioritized risks

D.
Qualitative analysis outcomes

Explanation:

The outcome of quantitative analysis can create a listing of prioritized risks that should be updated
in the risk register. The project team will create and update the risk register with fourkey
components: probabilistic analysis of the project, probability of achieving time and cost objectives,
list of quantified risks, and trends in quantitative risk analysis.
quantitative risk analysis.