You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes. Scrum is used as the process framework.
As a result of certain developments, the sprint you are working on may turn out to be dated.
Which of the following actions should you take?
A.
You should consider carrying on as normal.
B.
You should consider change the current sprints goal, without cancelling it.
C.
You should consider convert the current sprint into a template.
D.
You should consider cancelling the sprint.
Explanation: