You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You are making use of Microsoft Team Foundation Server (TFS) 2012 to manage the team you
are leading. You are in the process of creating a solution that has a number of external
dependencies. The solution also includes requirements that are well defined and will remain
unchanged. You have established that the project will be influenced in the event of an external
dependency, on the critical path, not meeting a committed deadline. This influence has to be
detected and calculated.
Which of the following should be used to administer your solution?
A.
You should consider making use of Microsoft PowerPoint storyboarding.
B.
You should consider making use of the Team Foundation Power Tools.
C.
You should consider making use of Microsoft Project.
D.
You should consider making use of the Feedback Manager tool.
Explanation: