Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
The process framework used by ABC.com’s development team, is Scrum. The team also makes
use of the Microsoft Framework (MSF) for Agile Software Development 6.0 process template.
ABC.com has assigned the product owner to a team member, named Mia Hamm, to whom Scrum
is unfamiliar. Mia Hamm is required to make sure that the product backlog is suitably arranged.
Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
The process framework used by ABC.com’s development team, is Scrum. The team also makes
use of the Microsoft Framework (MSF) for Agile Software Development 6.0 process template.
ABC.com has assigned the product owner to a team member, named Mia Hamm, to whom Scrum
is unfamiliar. Mia Hamm is required to make sure that the product backlog is suitably arranged.
Which of the following actions should you take?

A.
You should consider informing Mia Hamm to arrange the product backlog based on estimated
cost per requirement only.

B.
You should consider informing Mia Hamm to arrange the product backlog based on estimated
effort per requirement only.

C.
You should consider informing Mia Hamm to arrange the product backlog based on estimated
cost and effort per requirement.

D.
You should consider informing Mia Hamm to arrange the product backlog based on estimated
cost and effort per product.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *