Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You have been assigned as the team leader of a development team that makes use of the
Microsoft Visual Studio Scrum 2.0 process template. You have received instructions to acquire
requirements and tolerance standards, while also making sure that you are able to version and
track these standards using specific test cases.
Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You have been assigned as the team leader of a development team that makes use of the
Microsoft Visual Studio Scrum 2.0 process template. You have received instructions to acquire
requirements and tolerance standards, while also making sure that you are able to version and
track these standards using specific test cases.
Which of the following actions should you take?

A.
You should consider impediment work items.

B.
You should consider change request work items.

C.
You should consider including product backlog item (PBI) work items.

D.
You should consider including bug work items.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *