Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You are managing a ABC.com project. You are planning to track the amount of effort your team
has reported as complete for each sprint. Your solution should also allow you to estimate the
amount of backlog effort your team is able to deal with in forthcoming sprints.
Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You are managing a ABC.com project. You are planning to track the amount of effort your team
has reported as complete for each sprint. Your solution should also allow you to estimate the
amount of backlog effort your team is able to deal with in forthcoming sprints.
Which of the following actions should you take?

A.
You should consider analyzing the Impediment report.

B.
You should consider analyzing the Velocity report.

C.
You should consider analyzing the Build Summary report.

D.
You should consider analyzing the Release Burndown report.

Explanation: