You are the product owner for a new application.
You have the list of product backlog items (PBIs) with assigned business values for the first release of the
application.
You will be working with an established scrum master and development team. You know the team’s capacity
and the planned sprint duration.
You need to plan the release schedule based on yourexisting backlog.
Which three actions should you and the team perform? (Each correct answer presents part of the solution. Choose three.)
A.
Ask the development team to decompose the PBIs into individual tasks and estimate hours.
B.
Ask the development team to provide high level estimates to complete each PBI.
C.
Assign the PBIs to different sprints to define the release.
D.
Use the TFS 2012 task board features.
E.
Schedule the release using the Iteration Planningworkbook.
F.
Order the product backlog by business value.
BCE
should be BCF
would agree… from description, I would assume SCRUM (product backlog item) MSF SCRUM template has no “Iteration Planningworkbook”
I would say CEF.