You are utilizing the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process
template.
You need to track progress for the current sprint.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A.
Review team capacity.
B.
From the Product Backlog view of the current sprint, review the By Work capacity bars for each contributor.
C.
Review the task board.
D.
Review the burndown chart.
E.
From the project portal, review the Iteration Backlog spreadsheet.