A development team is attempting to use Scrum as its process framework. You join the team as the new
scrum master.
During a meeting, a developer states that his “taskis done”.
You need to describe to the team how the word “done” relates to Scrum.
What should you do?
A.
The word “done” indicates that code has been approved for release to production.
B.
The word “done” indicates that code compiles and has been unit tested.
C.
The word “done” indicates that code has been approved through testing and quality assurance.
D.
The word “done” must be defined, communicated, and agreed to by the team.