You manage a development team for a group of stakeholders that are physically remote from your
development center. Stakeholders have blocked out dates and times on their schedules for your team.
The stakeholders are concerned that several of the project requirements will not meet their needs due to
changing market conditions.
You need to ensure that the following requirements are met:
· Your team is doing effective and efficient work.
· The work is meeting the needs of the business.
· The project’s timeline is not at risk.
Which two actions should you perform? (Each correctanswer presents part of the solution.
Choose two.)
A.
Institute a policy of sign-offs for each requirement and design document.
B.
Develop a series of iterative proofs of concept that reflect a partial delivery of requirements and get
feedback from the product owner.
C.
Instruct the team to create a comprehensive set of design documents for each layer of the system.
Schedule a review with the stakeholders to get their feedback.
D.
Add a primary stakeholder to your team as the product owner.