You need to identify a critical path

(DRAG&DROP)
You have a list of tasks entered into Microsoft Visual Studio Team Foundation Server (TFS) 2012. Each task
has an estimated effort and assigned to a team member.
You have limited resources available. Due to external requirements, the start date and end date of thecurrent
iteration are fixed. Several of the tasks have dependencies on one another.
You need to identify a critical path.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer
area and arrange them in the correct order.)

(DRAG&DROP)
You have a list of tasks entered into Microsoft Visual Studio Team Foundation Server (TFS) 2012. Each task
has an estimated effort and assigned to a team member.
You have limited resources available. Due to external requirements, the start date and end date of thecurrent
iteration are fixed. Several of the tasks have dependencies on one another.
You need to identify a critical path.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer
area and arrange them in the correct order.)

A.

B.

C.

D.

Explanation:
1. Create predecessor/successor relationship between dependent tasks.
2. Create a query to return the tasks and open the in Microsoft Project,
3. Use Microsoft Project’s Tracking Gantt feature.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Cristian andres

Cristian andres

1. Create a query to return the tasks and open the in Microsoft Project,
2. Create predecessor/successor relationship between dependent tasks
3. Use Microsoft Project’s Tracking Gantt feature.

Use Microsoft Project’s Tracking Gantt feature.

Applying ALM with Visual Studio 2012 Jump Start – 05 Define End Value for the Software Iteration 54:17