Which three actions should you perform?

Your development team uses the Microsoft Visual Studio Scrum 2.0 process template. You are the scrum
master.
The product owner has created product backlog itemsand assigned them to a release. You need to work with
the development team to estimate when the release will be completed.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

Your development team uses the Microsoft Visual Studio Scrum 2.0 process template. You are the scrum
master.
The product owner has created product backlog itemsand assigned them to a release. You need to work with
the development team to estimate when the release will be completed.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

A.
Review the sprint backlog.

B.
Review the product backlog with the Forecast option set to on to determine if the release can be completed
based on the team’s velocity.

C.
Have the team create tasks for each item in the product backlog and assign hour estimates to the task.

D.
Review the sprint burndown chart.

E.
Set each team member’s per day capacity.

F.
Establish a sprint duration and a sprint velocity. Create enough sprints to complete the release.

G.
Estimate effort for each item in the product backlog.



Leave a Reply 2

Your email address will not be published. Required fields are marked *


realmandydee

realmandydee

Have any arguments about me submitting this on twitter?

JayFo

JayFo

This is quite good