What should you do?

You manage a project for which the team has not delivered all of the story points committed to in a previous
sprint.
You want to define the amount of work the team can commit to for the next sprint of the project.
What should you do?

You manage a project for which the team has not delivered all of the story points committed to in a previous
sprint.
You want to define the amount of work the team can commit to for the next sprint of the project.
What should you do?

A.
Review the sprint burndown to define the amount of work.

B.
Review the team velocity to define the amount of work

C.
Allow the product owner to define the amount of work.

D.
Review capacity of the team to define the amount ofwork.



Leave a Reply 0

Your email address will not be published. Required fields are marked *