You need to provide management with an earned value report for each project

You need to provide management with an earned value report for each project. What should you do?

You need to provide management with an earned value report for each project. What should you do?

A.
In Microsoft Office Project Professional 2007, create a visual report.

B.
In Microsoft Office Project Professional 2007, create a crosstab report by using the Report Wizard.

C.
In Microsoft Office Project Web Access, create a Data Analysis view.

D.
In Microsoft Office Project Web Access, export the Project Details Earned Value view to a spreadsheet.