You plan to report a bill of materials (BOM) as finished. You need to ensure that when you
report the BOM as finished, the following occurs: Component items from the BOM are
reported as finished. Component items from the sub-BOMs that are currently on-hand are
reported as finished. What should you set?
A.
The Reservation field to Automatic
B.
The Explosion option to Always
C.
The Explosion option to Shortage
D.
The Reservation field to Explosion
Answer: C
Explanation: The “explosion” parameter defines how AX will consume the on hand inventory of the components.
*Shortage: Sub BOMs are only exploded if there is insufficient on hand inventory. If there is a partial quantity of the Sub BOM available, AX will only explode the component quantities of the Sub BOM, for the difference.
C.