You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You have been asked what the purpose of using the standard cost of the service product used to
purchase the subcontracted service is.
What option suitably represents your reply?
A.
It allows for the cost of a subcontracted activity to be projected.
B.
It allows for all subcontracted activities to be standardized.
C.
It prevents the cost of a subcontracted activity to be projected.
D.
It sets the Update on hand on pick and Update on hand on receipt settings of a withdrawal
Kanban to No.
Explanation: