You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You have created a Lean Manufacturing production flow. You want to make sure that the materials
are changed into products.
Which of the following actions should you take?
A.
You should consider creating a process activity.
B.
You should consider including activity relations in the production flow.
C.
You should consider creating a transfer activity.
D.
You should consider configuring the use of optional activities
Explanation: