You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You have been instructed to generate an event Kanban for Kanban line events. You have been
informed that you have to make use of the manual process to achieve your goal.
Which of the following actions should you take?
A.
You should consider making use of the Kanban rules form.
B.
You should consider making use of the Kanban calculation policies form.
C.
You should consider making use of the Kanban quantity overview form.
D.
You should consider making use of the Kanban flow selection form.