What is the action you should take FIRST?

You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.

You have created a Lean Manufacturing production flow model. You are in the process of defining
a replenishment strategy that does not add value.
What is the action you should take FIRST?

You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.

You have created a Lean Manufacturing production flow model. You are in the process of defining
a replenishment strategy that does not add value.
What is the action you should take FIRST?

A.
You should consider setting the Kanban type to Manufacturing.

B.
You should consider setting the Kanban type to Withdrawal.

C.
You should consider setting the Kanban type to WIP.

D.
You should consider setting the Kanban type to Extraction.

Explanation: