You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You have created a Lean Manufacturing production flow model. You are preparing to configure the
Capacity Shortage Reaction for production flow model.
You want to make sure that a job processes when the throughput becomes available.
What action should you take?
A.
You should consider making use of the Postpone kanban scheduling method.
B.
You should consider making use of the Cancel kanban scheduling method.
C.
You should consider making use of the Add to the requested period kanban scheduling
method.
D.
You should consider making use of the Distribute kanban scheduling method.