What field should be configured next?

You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You have been instructed to configure the Takt time fields of a new Lean Manufacturing
production flow version. You have opened the Production flow versions details form.
You have configured the Per cycle unit of measure, Quantity per cycle, and Takt unit fields.
What field should be configured next?

You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You have been instructed to configure the Takt time fields of a new Lean Manufacturing
production flow version. You have opened the Production flow versions details form.
You have configured the Per cycle unit of measure, Quantity per cycle, and Takt unit fields.
What field should be configured next?

A.
The Required takt time field.

B.
The Maximum takt time field.

C.
The Minimum takt time field.

D.
The Average takt time field.