You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You are in the process of setting up a work cell for lean manufacturing. You have already created
a production flow model. You now need to configure a work cell to track labor costs.
What is the action you should take?
A.
You should consider defining a Scrap percentage via the Operation FastTab.
B.
You should consider defining the Capacity unit.
C.
You should consider defining the work cell as a bottleneck resource.
D.
You should consider defining a run time cost category via the Operation FastTab.
Explanation: