which criteria?

According to the ITIL v3 framework, a change that has an";approve"; status has met which criteria?

According to the ITIL v3 framework, a change that has an";approve"; status has met which criteria?

A.
The lab testing and operational assessments have been completed, and the change has been approved and committed to the change scheduler.

B.
The operational testing and technical assessments have been completed, and the change has been approved and committed to the change scheduler.

C.
The business and technical assessments have been completed, and the change has been approved and committed to the change scheduler.

D.
The lab testing and technical assessments have been completed, and the change has been approved but is not yet committed to the scheduler.