The project manager needs to determine the relationship between two variables. Which of the
following tools will the project manager use?
A.
Histogram
B.
Run chart
C.
Pareto chart
D.
Scatter diagram
Explanation:
The project manager needs to determine the relationship between two variables. Which of the
following tools will the project manager use?
The project manager needs to determine the relationship between two variables. Which of the
following tools will the project manager use?
A.
Histogram
B.
Run chart
C.
Pareto chart
D.
Scatter diagram
Explanation: