Which of the following is the earned value (EV)?

The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to
date. The project is currently 50 percent complete. Which of the following is the earned value
(EV)?

The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to
date. The project is currently 50 percent complete. Which of the following is the earned value
(EV)?

A.
$35,624.00

B.
$59,373.33

C.
$71,248.00

D.
$85,497.60

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *

sixteen − eight =