Which of the following represents the ETC of this project?

In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been
completed. The BAC is $900,000. Which of the following represents the ETC of this project?

In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been
completed. The BAC is $900,000. Which of the following represents the ETC of this project?

A.
$150,000

B.
$300,000

C.
$450,000

D.
$600,000

Explanation: