Which of the following are characteristics of a projects critical path?

Which of the following are characteristics of a projects critical path? (Select Two).

Which of the following are characteristics of a projects critical path? (Select Two).

A.
The critical path is the longest duration.

B.
The critical path has the least amount of resources.

C.
The critical path is the shortest duration.

D.
The critical path has less than or equal to zero float time.

E.
The critical path has a greater than zero float time.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *

sixteen + eleven =