Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?

Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?

Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?

A.
Exploiting

B.
Crashing

C.
Optimizing

D.
Fast tracking